Budhi Ganga Hydropower Project

b~XAwZez~-~r

Program & Progress

A. Bridge

  • Construction of the Bridge has been completed.

B. Access Roads to Dam site and Surge Tank

  • Construction of access road to dam site and surge tank has been completed.

C. Office Building and Other Facilities

  • Construction of Office Building and Other Facilities has been completed.

D. Detailed Engineering Design and Environmental Studies

  • Detailed Engineering Design Report and EIA Report of the project has been approved.
  • IEE Report of the Transmission Line has been approved.

E. Land Acquisition

  • Land Acquisition for civil works at Achham and Bajura and for substation at Doti has been completed. The Land Acquisition process for the transmission linetowers has been started.

F. Construction of the Bunker and other facilities

  • Construction of the bunker and other facilities has been completed.

G. Tendering of Major Construction Works and Consulting Service

  • Tendering and Procurement process of Lot 1: Civil and Hydro mechanical Works is ongoing.
  • GEODATA-BIDR-SIDEF JV has been selected as Owner’s Engineer for consulting services for major construction works .